Development of Al Ruwais Port

  • The project is under the supervision of Ashghal.

     

     Project started in early 2010.

     

     Project Expected to complete by 2014.

     

     Area of the port: Approximately 261, 224 square meters.

     

  • The main port’s components are:

    Container Berth - 531m.
    General Cargo Berth - 490m.
    -Dry and cold stores.
    -Storage areas.
    -Control tower, inspection platform and administration buildings.

    The port will be equipped with gantry cranes for container handlings, RTG cranes,mobile cranes and forklifts.

  • Current project status;

    -The marine works construction is ongoing.

    -Dredging of main channel is ongoing.

    -Construction of container and general cargo berth will complete in 2012.

    -Buildings and Port facilities are in design stage.